FAQ - What is a typical project timeline?

  1. Start-up meeting.
  2. Set-up site, project, workflow, reviews.
  3. Authoring of standard systems, liaise with supply chain, reviewing technical submittals, drawings etc to produce O&M descriptions, equipment schedules, literature, building logbook.
  4. Train the supply chain, pre-populate templates, set authoring task, responsibility.
  5. Manage VC meetings with your PM and chase any non-performing information suppliers. Minutes on the EDocuments platform.
  6. QA check of content for completeness of information and create maintenance links.
  7. Single upload of final certificates / as-built drawings - transmitted from project CDE.